Sa inilabas na update ng National Grid Corporation of the Philippines (NGCP), nananatiling hindi available ang suplay ng kuryente sa Camarines Norte, Camarines Sur, Albay at Sorsogon.
Partial naman nang naibalik ang suplay ng kuryente sa lalawigan ng Quezon at Batangas.
Habang normal na ang suplay ng kuryente sa Cavite at Laguna.
Narito ang mga hindi pa rin available na linya sa Southern Luzon:
Batangas-Mabini 69kV Line
Date/Time Out: 1 November 2020, 1:22PM
Customer affected: BATELEC II
Batangas-Bauan 69kV Line
Date/Time Out: 1 November 2020, 3:06PM
Customer affected: Meralco, First Bay Power Corp.
Batangas-Ibaan-Rosario 69kV Line
Date/Time Out: 1 November 2020, 5:46PM
Customer affected: BATELEC II, Ibaan Electric Corp.
Calaca-Balayan-Nasugbu/Calatagan 69kV Line
Date/Time Out: 1 November 2020, 3:04PM
Customer affected: BATELEC I
Gumaca-Lopez 69kV Line
Date/Time Out: 1 November 2020, 10:44AM
Customer affected: QUEZELCO I
Gumaca-Atimonan 69kV Line
Date/Time Out: 1 November 2020, 12:34PM
Customer affected: QUEZELCO I
Pitogo-Mulanay 69kV Line
Date/Time Out: 1 November 2020, 11:25AM
Customer affected: QUEZELCO I
Labo-Paracale 69kV Line
Date/Time Out: 1 November 2020, 6:36AM
Customer affected: CANORECO
Labo-Talisay 69kV Line
Date/Time Out: 1 November 2020, 6:26AM
Customer affected: CANORECO
Naga-Libmanan 69kV Line
Date/Time Out: 31 October 2020, 7:59PM
Customer affected: CASURECO I
Naga-Lagonoy 69kV Line
Date/Time Out: 1 November 2020, 4:16AM
Customer affected: CASURECO II, CASURECO IV
Naga-Tinambac 69kV Line
Date/Time Out: 1 November 2020, 5:50AM
Customer affected: CASURECO II
Naga-Concepcion 69kV Line
Date/Time Out: 1 November 2020, 5:53AM
Customer affected: CASURECO II
Naga-Iriga 69kV Line
Date/Time Out: 1 November 2020, 6:04AM
Customer affected: CASURECO III
Daraga-Sorsogon 69kV Line
Date/Time Out: 1 November 2020, 4:24AM
Customer affected: SORECO I, SORECO II
Sorsogon-Bulan 69kV Line
Date/Time Out: 1 November 2020, 4:24AM
Customer affected: SORECO I, SORECO II
Sorsogon-Sorsogon 69kV Line
Date/Time Out: 1 November 2020, 4:24AM
Customer affected: SORECO II
Ligao-Dunao 69kV Line
Date/Time Out: 1 November 2020, 3:37AM
Customer affected: APEC
Daraga-Ligao 69kV Line
Date/Time Out: 1 November 2020, 3:37AM
Customer affected: APEC
Tiwi-Malinao-Tabaco 69kV Line
Date/Time Out: 1 November 2020, 4:52AM
Customer affected: APEC
Daraga-Legazpi 69kV Line
Date/Time Out: 1 November 2020, 5:55AM
Customer affected: APEC
Daraga-Sto. Domingo 69kV Line
Date/Time Out: 1 November 2020, 5:55AM
Customer affected: APEC
Nakakalat na ang mga line crew ng NGCP at nagsasagawa ng aerial at ground patrols para mai-assess ang pinsala ng bagyo at mapabilis ang restoration ng kuryente.