Overall progress rate ng Bicol International Airport, nasa 70.89 porsyento na

By Angellic Jordan December 15, 2020 - 03:16 PM

DOTr photo

Umabot na sa 70.89 porsyento ang overall progress rate ng Bicol International Airport (BIA) sa Daraga, Albay.

Ayon sa Department of Public Works and Highways (DPWH), hangganh November 30, 2020, 85.97 porsyento nang tapos ang Package 2A ng airport development project.

Sakop nito ang pagtatayo ng landside facilities at iba pang gusali.

Samantala, ang Package 2B naman ay 45.39 porsyento nang kumpleto kung saan kasama ang PTB, runway extension, taxiway, drainage, at iba pang site development works.

Oras na matapos ang paliparan, kaya nitong ma-accommodate ang dalawang milyong pasahero kada taon.

Makatutulong ito sa air traffic at tourist arrivals sa Bicol region.

DOTr photo

TAGS: BIA in Albay, BUILDBUILDBUILD, DPWH, DPWH project, Inquirer News, Overall progress rate Bicol International Airport, Radyo Inquirer news, BIA in Albay, BUILDBUILDBUILD, DPWH, DPWH project, Inquirer News, Overall progress rate Bicol International Airport, Radyo Inquirer news

Disclaimer: The comments uploaded on this site do not necessarily represent or reflect the views of management and owner of Cebudailynews. We reserve the right to exclude comments that we deem to be inconsistent with our editorial standards.